DBA Implementation

From DE4A
Jump to navigation Jump to search

This page will contain lessons learned, tips and tricks on implementing the solution for Doing Business Abroad.

Tips for new Member States implementing and using the DE4A Connector

  • Use connectathons as early as possible to share experiences in the setup and resolve issues together.
  • Use the publicly available playground and instructions to set up and configure the national DE4A Connector.
  • Configure the DE4A Connector using a less strict setup for cryptographic validation, to to sort out connectivity issues. Trying to solve issues with strict cryptographic adherence is difficult as the encryption can cause errors, that are not related to the actual functionality and connectivity.

Tips for new Member States implementing and using eIDAS and validating the mandates of representatives

... to be added ...

Establishing connections

The DBA pilot is establishing and testing connections between participating Member States, using testcases and connectathons. During specific timeslots, experts of 2 (or more) countries join with technical experts of the DE4A program. The meetings are online, and focus on establishing the connection between DE4A Connectors or eIDAS nodes. Pre-defined testcases are used to collect necessary proof that the connection is functioning correct. Any last-minute errors are being resolved immediately (if possible).

DE4A Connector

Process

For establishing connections between DE4A Conectorsof participating Member States the following steps are performed:

  • Preparation
    • collecting necessary information for configuration of the common components.
  • Local testing
    • setting up the national DE4A Connector and connecting this to a DE4A Connector in the DE4A playground.
  • Conectivity testing
    • testing a full chain of components, using a Mocked DE, the national DE4A Connector (acting as a DT or DR), the playground DE4A Connector (acting as a DR or DT) and a Mocked DE.
  • Connectathon
    • testing a full chain of components, using a Mocked DE, one national DE4A Connector (acting as a DT or DR), another national DE4A Connector (acting as a DR or DT) and a Mocked DO (Milestone 2 and 3)
    • testing a full chain of components, using a real DE, one national DE4A Connector (acting as a DT or DR), another national DE4A Connector (acting as a DR or DT) and a real DO (Milestone 4)

During the OOP TS connectathons, these test cases and preparations are being used / executed.

File:20210615 Test cases DE4A cross-border.xlsx

Planning DE4A Connector connectathons

For each milestone, connectathons are scheduled according to the tables below.

DE4A Connector Milestone 2 and 3 (Only with DE4A Connectors)
DT
AT NL RO SE
DR AT Probably September Probably September August 30th / September 3rd
NL Probably September June 1st/4th

(to be completed July14th/16th)

August 30th / September 3rd
RO Probably September June 1st/4th

(to be completed July14th/16th)

August 30th / September 3rd
SE August 30th / September 3rd August 30th / September 3rd August 30th / September 3rd
DE4A Connector Milestone 4 (Also with DO and DE)
DT
AT NL RO SE
DR AT October / November October / November October / November
NL October / November October / November October / November
RO October / November October / November October / November
SE October / November October / November October / November

eIDAS nodes

Connections between eIDAS nodes are established using existing eIDAS procedures and are scheduled in these timeslots:

eIDAS Milestone 1
Proxy
AT NL RO SE
Connector AT July 5th/9th July 12th/16th (likely later) (will be rescheduled)
NL July 5th/9th (likely later) July 12th/16th (will be rescheduled)
RO July 12th/16th (likely later) July 12th/16th (will be rescheduled)
SE (will be rescheduled) (will be rescheduled) (will be rescheduled)