DBA Implementation

From DE4A
Revision as of 11:48, 26 January 2022 by Ard.vanderheijden (talk | contribs)
Jump to navigation Jump to search

Back to Doing Business Abroad main page

[Draft]

This page contains the process, planning and status of establishing connections between participating Member States is presented.

Establishing connections

The DBA pilot is establishing and testing connections between participating Member States, using testcases and connectathons. During specific timeslots, experts of 2 (or more) countries join with technical experts of the DE4A program. The meetings are online, and focus on establishing the connection between DE4A Connectors or eIDAS nodes. Pre-defined testcases are used to collect necessary proof that the connection is functioning correct. Any last-minute errors are being resolved immediately (if possible).

DE4A Connector

Process

For establishing connections between DE4A Conectors of participating Member States the following steps are performed:

  1. Preparation
    • collecting necessary information for configuration of the common components.
  2. Local testing
    • setting up the national DE4A Connector and connecting this to a DE4A Connector in the DE4A playground.
  3. Connectivity testing
    • testing a full chain of components, using a Mocked DE, the national DE4A Connector (acting as a DT or DR), the playground DE4A Connector (acting as a DR or DT) and a Mocked DO.
  4. Connectathon
    • testing a full chain of components, using a Mocked DE, one national DE4A Connector (acting as a DT or DR), another national DE4A Connector (acting as a DR or DT) and a Mocked DO (Milestone 2 and 3)
    • testing a full chain of components, using a real DE, one national DE4A Connector (acting as a DT or DR), another national DE4A Connector (acting as a DR or DT) and a real DO (Milestone 4)

During the OOP TS connectathons, these test cases and preparations are being used / executed. File:20210824 Test cases DE4A cross-border AT-NL-RO-SE.xlsx

Planning DE4A Connector connectathons

For each milestone, connectathons are scheduled according to the tables below.

DE4A Connector Milestone 2 and 3 (Only with DE4A Connectors)
DT
AT NL RO SE
DR AT August 30th / September 3rd August 30th / September 3rd August 30th / September 3rd
NL August 30th / September 3rd June 1st/4th

(completed July 14th/16th)

August 30th / September 3rd
RO August 30th / September 3rd June 1st/4th

(completed July 14th/16th)

August 30th / September 3rd
SE August 30th / September 3rd August 30th / September 3rd August 30th / September 3rd
DE4A Connector Milestone 4 (Also with DO and DE)
MS acting as DP
AT NL RO SE
MS

acting

as DC

AT tbd tbd N/A
NL 29/30 November 29/30 November N/A
RO 29/30 November 29/30 November 29/30 November
SE 29/30 November 29/30 November 29/30 November

eIDAS nodes

Connections between eIDAS nodes are established using existing eIDAS procedures and are scheduled in these timeslots:

eIDAS Milestone 1
Proxy
AT NL RO SE
Connector AT July 12th/16th (will be rescheduled) (will be rescheduled)
NL July 12th/16th July 5th/9th (will be rescheduled)
RO (will be rescheduled) July 5th/9th (will be rescheduled)
SE (will be rescheduled) (will be rescheduled) (will be rescheduled)



Status of connections

The current status of participating Member States having established connections is displayed in the tables below:

eIDAS Milestone 1: Connecting eIDAS proxies and connectors
Proxy
AT NL RO SE
Connector AT
NL
RO
SE
OOP TS Milestone 2/3: Connecting DE4A Connectors between Member States
DE4A Connector acting as DT
AT NL RO SE
DE4A Connector

acting

as DR

AT
NL
RO
SE
OOP TS Milestone 4: Connecting DE4A Connectors, Data Evaluators and Data Owners between Member States
MS acting as DP
AT NL RO SE
MS

acting

as DC

AT N/A
NL N/A
RO
SE

Green = Connection established

Yellow = Connection partlially established (issues remaining to be solved)

Red = Connection not established yet